A common story about data centers and insurance is that insurers are pricing the industry out of the market. The numbers do not show that. Marsh's index for the third quarter of 2026, released October 21, has US property insurance rates down 10%, matching a 10% drop globally that was the largest of any line of business. Aon's Ryan Barber told an industry forum in early October that there is ample capacity for data center projects valued at $3 billion to $5 billion, and that placements above $10 billion are now possible. The strain is somewhere else: in the size of the biggest sites, and in how many of them an insurer is willing to hold in one place.

A soft market, and a ceiling at the top

Marsh's release does not mention data centers, but it describes ample capacity and strong competition across major lines of insurance, which is the backdrop to the data center story. Within that market, the largest campuses are a different kind of risk. Swiss Re Corporate Solutions says a traditional data center once needed about $2 billion in limits, while one hyperscale campus can now require $20 billion for the buildings alone. S&P Global Ratings puts the insurable value of the largest projects at as much as $30 billion. Brokers say Munich Re will take roughly $250 million net on a single data center construction project, so reaching $10 billion on one site means stacking a tower across 40 or more carriers.

Zurich's figures show how fast the scale moved. The average insured data center project there rose from about $150 million to $3 billion in five years, and Zurich's head of construction and surety, Kelly Kinzer, has said the market does not have enough capacity to insure these projects at full value. Zurich's 2026 US report, as summarized by a construction law firm, found that many projects are insured for only one-third to one-half of their total value. The same summary says some projects reportedly carry limits of $2 billion to $5 billion on campuses worth many times that. Insurers increasingly size coverage to an estimated or probable maximum loss, not to the full replacement cost.

The problem is concentration

Barber called tracking accumulation the biggest struggle right now for insurers and reinsurers. Campuses are built in phases, which leaves an insurer holding builders risk on one building and operating property exposure on the next, at the same address. The contents add to it. Computing equipment is often several times more valuable than the buildings that house it, Facilities Dive reported in its coverage of MSIG USA, and S&P's Patricia Kwan said insurers are not designed for that level of concentration in one location. The geography is also shifting: Zurich reports that 64% of capacity under construction in 2026 is outside traditional hubs such as Northern Virginia, so insurers are being asked to underwrite new locations as well as larger sites.

What goes wrong: fire, weather, and waiting for equipment

Allianz Commercial's analysis of 221 data center claims, worth about $782 million, found that fire drives severity. Fire accounted for well over half the value of those claims even though it was only 14% of claims by number. Water damage was the most frequent claim, at 21%, and willful acts, including crime and cyber crime, made up 19%. Allianz points to lithium-ion batteries built into server racks, in place of separate battery rooms, as a source of thermal runaway, and the report notes a 2025 fire at a South Korean government data center in Daejeon, believed to have started with a battery explosion, that shut down 600 servers. Tyler Ahrenhold of MSIG USA said on-site turbines or batteries raise the risk of fire or explosion tenfold compared with a grid-only site, and that his company asks for at least 100 feet between a power source and a building. He added that insurers rely on best practices because no code addresses the spacing.

Weather is the other large driver. Severe weather has been the leading cause of loss in Zurich's US data center builders risk portfolio for three years. Swiss Re's modeling puts more than a quarter of US data center capacity in areas with three or more large-hail days a year, and over 40% in zones with significant to very high tornado risk. Then there is waiting. Allianz cites Schneider Electric modeling in which business interruption makes up almost a third of climate-related losses, with more than 90% of that coming from upstream supply chain disruption rather than direct damage, and it notes switchgear lead times of up to 80 weeks and transformer lead times of up to 50 weeks. It also describes a startup delay caused by power disturbances that produced a loss of 50 million to 100 million euros at one hyperscale facility. Coverage for delay in startup has become harder and more expensive to buy at meaningful limits, according to the construction law firm's summary of the Zurich report.

Who holds the gap

When insurance falls short of full value, someone else holds the difference. S&P's Kwan said lenders generally want full-value protection and resist coverage sized to maximum loss, and that any uninsured gap flows back to the sponsor and shows up in the ratings of the data center's debt. The construction lawyer Kenny Cantrell argues that contracts, more than policies, are becoming the main way the financial consequences of a major loss get divided, with owners and contractors both scrutinizing indemnities, liability caps and delay provisions.

The industry is also looking for more capital. Zurich's Kinzer said he expects talks about securitizing data center insurance risk to become more necessary as project values rise, though he said the market is not there today. Euler ILS Partners is working with insurers to underwrite specialist data center policies, and investors in insurance-linked securities, who typically take damage risk but not the risk that a data center proves unprofitable, have asked Aon how to take part. Premiums are expected to grow. Swiss Re's Michael LaRocca projects data center premiums rising toward $24 billion from about $10.6 billion today, S&P estimates that construction coverage alone could generate about $10 billion in premiums this year, and Barber estimates more than $100 billion in new premiums over the next five to ten years. Liberty Mutual's Marc Orloff cautioned that the premium is not fully recurring, because builders risk premium falls if construction slows.

What to watch

Several open questions follow from this. One is whether lenders keep accepting coverage below full value as campuses grow past what the market can place. Another is whether securitization and specialist capital arrive in time to matter. A third is whether fire standards for on-site power catch up, since insurers are filling a gap that codes leave open. And the equipment and supply-chain exposure ties back to the long lead times the Digest covered in its piece on transformers. None of the sources predicts a particular outcome. What they describe is an insurance market with plenty of room for the average project, and a hard limit on the largest ones.