Voters favored limiting data center development in 40 of 41 local ballot measures on November 3, according to Ballotpedia. In Trenton, Ohio, Issue 17 banned data centers above 25 megawatts and passed with about 80 percent of the vote, per unofficial results. On November 12, Prologis sued the city, arguing the amendment cannot apply to its permitted, substantially constructed 250-megawatt project, in which it says it has invested more than $42 million. In Bethlehem, Pennsylvania, the Planning Commission voted 5-0 on November 12 to approve a data center submitted before new zoning rules took effect in October.
The Trenton suit tests whether new local restrictions can reach projects already permitted under earlier rules, a question many jurisdictions adopting limits may face. The Bethlehem vote shows a project filed before a zoning change can proceed under the old ordinance. Developers with approvals in hand and communities seeking to halt them are likely to cite both cases.
The headline signals a national trend of new local zoning laws constraining data center construction, which is relevant to US policy. It ranks below the single formal decision because the snippet gives no specific jurisdiction or action.