The Loudoun County Board of Supervisors voted 7-1, with one abstention, to pause consideration of data center and substation applications for up to 12 months, backdated to September 15, 2026. The pause gives the county time to finish updating its data center policies. Supervisor Juli Briskman, who led the effort, called it "a major step forward for our residents and communities." Meeting documents show 33 active applications, and county staff said the pause could prompt developer lawsuits and that clearing the backlog after September 2027 could take months.
Loudoun County had 245 data centers in operation and under development, and the county's 2027 budget projects $1.3 billion in data center revenue, or 40 percent of the total budget. A pause there freezes new projects in what the article calls the global center of data center development. State Sen. Russet Perry has also proposed a three-year statewide moratorium from July 1, 2027, which could widen the block beyond Loudoun.
The snippet reports a formal 12-month moratorium adopted in Loudoun County, Virginia, the largest US data center market. A government body enacting a formal rule ranked it first in this run.