The Lansing Town Board voted 3-2 to ban data centers, but the result may not stand. TeraWulf, the company behind the proposed data center, led a petition that would require a supermajority of four votes under New York Town Law, which allows owners of 20 percent or more of the affected land to challenge a zoning change. The petition was signed by 71 people who said they own or represent 202 tax parcels. Town officials are still verifying it, and it is unclear when that review will finish; the town clerk did not announce whether the motion passed.

Why this matters

A landowner petition could turn a simple-majority zoning ban into a measure needing four of five votes, which gives a developer a legal tool against local restrictions. The town withdrew an earlier moratorium on large developments in November 2025 after legal threats from TeraWulf, so the dispute is part of an ongoing conflict.

Why the Digest selected this story

The headline points to a municipal data center ban whose status is unresolved. That is a local government rulemaking story and it adds to the ongoing wave of local moratoriums and bans.

Read the full story at The Ithaca Voice →